FY 19-20 Street Improvement Project In Progress

FY 2019-20 Street Improvement Project Streets and Type of Work


Dorothea Rd.

  • Cold Mill 2” & Install 2” Asphalt Cap from Avocado Crest Rd to Nabal Rd.
  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from Cypress St. to Avocado Crest Rd.
  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from Cypress St. headed North to End

Cypress St.

  • Cold Mill 2” & Install 2” Asphalt Cap from Mayapan Rd. to Nabal Rd.
  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from Nabal Rd. to Avocado Crest Rd.

Ganter Rd.

  • Cold Mill 2” & Install 2” Asphalt Cap from Cypress St. to End.

Nabal Rd.

  • Cold Mill 2” & Install 2” Asphalt from Cypress St. to 800 ft South of Dorothea Rd.
  • Cold Mill 2” & Install 2” Asphalt Cap from Dorothea Rd to Tumin Rd.
  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from 800 ft South of Dorothea Rd. to Dorothea Rd.

Popenoe Rd.

  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from Kashlan Rd to Oleander Rd. 

Kashlan Rd.

  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from Cypress St. to Popenoe Rd.

Rincon Dr.

  • Crack Seal & Slurry Seal from Peppertree Dr. thru the Cul-de-sac

Hiatt St.

  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from Walnut St. to End

Mayapan Rd.

  • Cold Mill 2” & Install 2” Asphalt from Cypress St. to End

Darlene Dr.

  • Cold Mill 2” & Install 2” Asphalt from Mayapan Rd to End

Bonita Dr.

  • Cold Mill 2” & Install 2” Asphalt from Peppertree Dr. thru the Cul-de-sac

La Cresta Dr.

  • Crack Seal & Slurry Seal (with Minor AC Dig outs) from Peppertree Dr. thru the Cul-de-sac

Avocado Crest

  • Crack Seal from Lamat Rd. to Dorothea Rd.

Sierra Vista Road

  • Crack Seal from South City Limit thru the cul-de-sac

Walnut Street

  • Crack Seal from Via Miguel to Hiatt St.